Engineer’s Corner: Trench Shield Inspection and Repair

August 11, 2017

It is well understood that the use of shoring equipment requires regular inspection and maintenance. Understanding how to inspect a shoring device, what needs to be focused on and how to make practical decisions about what is observed is not so clear.  Steel shoring shields have very long life times, ...

Slide Rail System Provides Positive Shoring Alongside DOT Roadway

August 11, 2017

A contractor had been tasked with setting a new manhole inlet tying into an existing 60 -in storm drain, which would ultimately help regulate storm water for toll roads.  The excavation would require a 12-ft square excavation to a depth of 16-ft in what the contractor had classified as a ...

Slide Rail System Used For Campus Infrastructure Project

August 11, 2017

A contractor was extending a drainage tunnel as part of infrastructure support for a growing Texas university.  The contractor would need to excavate 300 lineal feet to a depth of 12-ft and with a width of 16-ft to accommodate the 10-ft square drainage tunnel.  The contractor had classified the sandy ...

Engineer’s Corner: National Trench Safety Develops a New Lecture Series

July 17, 2017

OSHA Subpart P was promulgated starting in 1970 when Federal OSHA was established and adopted it as a “National Consensus Standard” in 1989. At that point it became a law that employers had to adhere to and could be cited for violating it. In my personal opinion, the standard has ...

Davit Arm Solves Jobsite Safety Need

July 17, 2017

A Mid-Atlantic contractor was installing piping and pumps in a 30-ft deep wet well.  The contractor needed a safe way to lower equipment into the wet well and allow the crew the tools to complete the project, as the site would not have sufficient room to install scaffolding. The contractor called ...

Steel Sheeting Guide Frame System Provides Necessary Soil Support

July 17, 2017

 A contractor was performing a storm water infrastructure upgrade tying drainage into an existing manhole.  The project would require a 16-ft long, 12-ft wide and 14-ft deep excavation in a sand and clay mixture that the Competent Person had classified as a Type C soil. The project occurred on a ...

National Trench Safety Announces Opening of New Fort Worth, Texas Operation

June 12, 2017

HOUSTON, T.X.—National Trench Safety, LLC (NTS), a Houston-based company specializing in the rental and sales of trench and traffic safety equipment, trench and traffic safety engineering, and OSHA-compliant training classes, announced today the opening of a new branch operation in Fort Worth, Texas. “We’re excited to be strengthening our presence ...

Engineer’s Corner: Excavation Shoring Equipment Job Hazard Analysis

June 7, 2017

On June 19th through 24th, the National Utility Contractors Association (NUCA) will be sponsoring a Trench Safety  Stand-Down to raise awareness and prevent accidents in excavation work.  One of the major ideas behind a safety stand-down is to increase awareness and focus on safety by encouraging participatns to stop, think ...

Slide Rail System with Tie Back Provides Necessary Soil Support for Large Precast Tank Installation

June 7, 2017

A Southwest contractor would be installing a concrete cooling tank that was used in the project owner’s business manufacturing process. The concrete cooling tank would be precast and would need to be installed in three sections, with each section weighing about 90,000 pounds.  The components would require an excavation of approximately ...

Hydraulic Excavation Brace Saves Contractor Time and Money

June 7, 2017

A Central Florida contractor was performing one portion of a water expansion project that would require a bore beneath existing rail tracks. The contractor estimated the excavation would need to be about 40-ft long, 16-ft wide and about 19-ft deep to provide the necessary room to operate the boring machine ...